50Hertz is installing the Cluster Westliche Adlergrund 2 (CWA2) in the German Exclusive Economic Zone (EEZ) in the Baltic Sea. A new submarine high-voltage cable grid to connect various offshore wind farms to their offshore substations. It also transports the electricity to the mainland. AECOM supports this large construction project with multiple experts from planning until delivery.

AECOM is currently delivering expertise to support 50Hertz in their operations for the duration of the project. This multiple-year contract includes all phases of the project; surveying, boulder and UXO removal, trenching, cable-laying and backfilling. AECOM is responsible for Lead Offshore Installation Management and Marine Operations Management.

As part of the offshore site management, we develop, supervise and coordinate the installation process and operations on the offshore construction site.

This also includes budget planning, documentation and preventing and recovering of interrupted workflows related to the installation schedule.

Furthermore AECOM delivers Logistics Management Services. As full-time member of the team on site, we handle all logistics-related topics, such as planning of transport, material and personnel as well as all relevant documentation. AECOM also acts as the liaison between the port and customs authorities and the client.